12th Street, Minnesota Avenue to Summit Avenue

12th

Project Milestones

  1. Phase 1 – removal of existing surfacing west side of Summit Ave to West side of Spring Ave
  2. Phase 1 – installation of water main pipe and other underground utility work
  3. Phase 2 – removal of existing surfacing west side of Spring Ave to Minnesota Ave
  4. Phase 2 – installation of water main pipe and other underground utility work
  5. Phase 1 & 2 – final grading, curb / gutter installation
  6. Phase 1 & 2 – asphalt paving
     

Commuter Route Information

  • Traffic will be closed on 12th Street for Phase 1 construction from west of Summit Ave to west of Spring Ave.  
  • Traffic will be closed on 12th Street for Phase 2 construction from west of Summit Ave to west of Minnesota Ave. 
  • The intersections of 12th & Summit & 12th & Duluth will be closed for the entirety of the project, with 12th & Spring Ave intersection closed for Phase 2.   
  • A Pedestrian detour route will be provided at Summit Avenue for Phase 1 construction.
  • A pedestrian detour route will be provided at Minnesota Avenue for Phase 2 construction.

Sign Up for Notifications

Project Overview

Estimated Completion Date:

50 Working Days and by November 1, 2019 

Contract Amount:

$682,876.94 

Project Summary:

This project will reconstruct 12th Street between Minnesota Avenue and Summit Avenue.  Improvements include new water main, sanitary sewer repairs, storm drainage repairs, street light improvements, new accessible curb ramps, curb and gutter, and asphalt surfacing. 

Contact Information

City of Sioux Falls

Kari Drake, Project Manager
kdrake@siouxfalls.org
605-367-8611, (office)
605-777-2859 (cell)

 

Consultant Name:

Sayre Associates
Zach Kiesow
zachk@sayreassociates.com 
605-332-7211 (office) 
605-370-1948 (cell)

 

Contractor Name

Asphalt Surfacing Company