2019 Kingswood Way Drainage Improvements

Kingswood

Project Milestones

Phase 1A

32nd Street - Karen Drive to Royal Court

  1. Remove existing street section
  2. Install Storm Drainage Pipe
  3. Install Water Main
  4. Replace curb and gutter
  5. Replace Sidewalk and Accessible Curb Ramps
  6. Replace street surfacing

Phase 1B

Kingswood Way - 32nd Street to Walden Drive:

  1. Remove existing street section
  2. Install Storm Drainage Pipe
  3. Install Water Main
  4. Replace curb and gutter
  5. Replace Sidewalk and Accessible Curb Ramps
  6. Replace street surfacing

Phase 2

Kingswood Way - Walden Drive to 36th Street; 36th Street - Steven Drive to Gibson Avenue; and Steven Drive - 36th Street to 37th Street: 

  1. Remove existing street section
  2. Install Storm Drainage Pipe
  3. Install Water Main
  4. Replace curb and gutter
  5. Replace Sidewalk and Accessible Curb Ramps
  6. Replace street surfacing
     

Commuter Route Information

Phase 1A - 32nd Street - Karen Drive to Royal Court: Traffic will be detoured to 26th Street and 36th Street

Phase 1B - Kingswood Way - 32nd Street to Walden Drive: Kingswood Way closed to traffic.  Residents will not be allowed to park in their driveways while work is occuring.

Phase 2 - Kingswood Way - Walden Drive to 36th Street; 36th Street - Steven Drive to Gibson Avenue; and Steven Drive - 36th Street to 37th Street: Kingswood Way, 36th Street, and Steven Drive closed to traffic. Residents will not be allowed to park in their driveways while work is occuring.

 

Sign Up for Notifications

Project Overview

Estimated Completion Date:

Start on or after April 29; Complete within 85 Working Days and by October 1, 2019; Seeding complete by November 15, 2019 

Contract Amount:

$1,267,648.15 

Project Summary:

This project will reconstruct Steven Drive from 37th Street to 36th Street; 36th Street from Steven Drive to Kingswood Way; and Kingswood Way from 36th Street to 32nd Street. Work includes installation of new storm drainage pipe, water main repairs, partial replacement of curb and gutter, new accessible curb ramps, street light improvements, and new asphalt surfacing. 

Contact Information

City of Sioux Falls

Tim Krueger, Project Manager
tkrueger@siouxfalls.org 
605-367-8615 (office)
605-940-5280 (cell)

Consultant Name:

Banner Associates, Inc.
Joe Munson, PE
Banner Associates, Inc.
joem@bannerassociates.com
1-855-323-6342
605-941-4276

Alex Welbig
Banner Associates, Inc.
alexw@bannerassociates.com
1-855-323-6342
605-261-8212

Contractor Name

Winter Brothers Underground, Inc.