Overlay Program

Update: 05/17/2019

Concrete repairs are currently working in areas 9 and 12. We are scheduled to mill and overlay area 13 and 1 in late- May. The utility conctractor Backhaus Excavation and Underground, LLC is scheduled to start areas 6, 8, and 15 during the week of May 20th. 

The contractors completing the concrete work are Holstein Excavating and Triple R Paving. The contractor completing the utility repairs is Backhaus Excavation and Underground, LLC. 

For an estimate time when work will be in your neighborhood, check the schedule below.

Please see Frequent Asked Questions on the Overlay program below. If you have additional questions, please contact one of the team members listed or email Nick Rezac at nrezac@siouxfalls.org

 

Overlay Program Schedule

View Map of Projects

Location Concrete Work Utility Work Asphalt Mill & Overlay
1-Ash Grove 2 Area: Briarwood Ave to Arden Ave from Briar Den Court to 62nd Street, Including 61st Street West of Cliff Completed N/A Late May
2-Suburban Area: 18th Street to 22nd Street from Sycamore to Gordon Drive Completed N/A Late May
3-Village Square Area: Village Square Circle, South of 26th Street Completed N/A Mid June
4-Dubuque Avenue Area: North of 6th Street Completed N/A Mid June
5- Aaron 1 Area: Aaron Ave, 62nd Street and 66th Street Completed Late May Mid June
6-Oxford East Area: 26th Street to Westminster Dr & Oxford Ave to Valley View Road Completed In-Progress Late June
7-Aaron 2 Area: North of 66th Street & West of Sundowner Ave Late May N/A Early July
8-Strabane and Chesapeake Ln Area: West of Sertoma Ave Mid June In-Progress Mid July
9-Caraway Drive and Sunflower Trail Area: South of 57th Street In-Progress Late May Mid July
10-Lyons Area: South of 12th Street I29 to River Early July Mid June Late July
11-Norton Area: South of 26th Street Late May Early June Late July
12-Ralph Rogers Area: West of Western Ave & North of 69th Street In-Progress Mid July Late August
13-Minnesota Ave Area: 4th-7th Street May N/A Late May
14-6th Street Area: South of 6th Street and East of Sycamore Ave Mid June Late June 2020
15-Anderson Drive Area: West of Marion Road at 33rd Street Late July In-Progress 2020
16- 56th Street Area: Cliff Ave to North 4th Late June Late June 2020

faqs

If your sprinkler system needs to be repaired because of the curb and gutter installation, we apologize for the inconvenience. Sprinkler damage is sometimes unavoidable during curb and gutter repairs due to the proximity of the heads to the work area. Please contact us to get more information on the process to get it repaired.

Where concrete repairs are made, disturbance to lawns is an inevitable part of the process. The contractor will reseed areas impacted by the concrete construction. If concrete repairs in your neighborhood are finished between June and August, seed will not typically be planted until the fall. We wait to reseed during these months because of the challenge for the grass to grow during this time.

Although the contractor will be responsible for watering for several weeks, we recommend that you supplement the contractor’s watering to accelerate grass growth. Turf grasses generally require 1 inch of water per week. Even with proper maintenance, it could take up to two years to reestablish the lawn to the preconstruction condition. You may take additional measures to expedite the restoration process such as overseeding, fertilizing, or weed control.

If weeds grow before the grass, please mow the restored areas and the grass will eventually catch up and fill the restored area. Typical lawn maintenance will control many varieties of nuisance weeds. The contractor will employ weed control measures, but some cannot be performed for several weeks after grass germination to protect the new grass.

The maintenance and repair of your driveway approach and the associated gutter are your responsibility. If your approach is in need of repair, now may be a good time to perform this work. Driveway approaches and associated gutter will not be replaced as a part of this project. In the picture below, the area shaded in blue (driveway approach and the gutter in front of approach) are the property owner’s responsibility.

If you choose to have your driveway approach replaced before the mill and overlay, you will not have to pay for the asphalt patch (18-inch area shaded in gray) that is typically needed when replacing the approach.

Please let us know if you plan on replacing your driveway approach before the asphalt overlay. The contractor performing the work will need to be bonded and insured and receive a permit from City Engineering before starting the repair.

Driveway approach

The Street Division will drop off an informational door tag to let you know when crews plan to mill, tack, and overlay your street. If you have any questions on the schedule for paving your street, contact the Street Division at 605-367-8255.

Occasionally, crews are working in an area where a graduation party or neighborhood rummage sale is scheduled. Due to the frequency of these events and limited time for construction, we unfortunately can’t avoid them all. If you have an event planned, let one of our team members know the details. We will try to avoid working in the area at that time. If work at that time is unavoidable, we will work with the contractor to be as accommodating as possible.

Overlay projects typically progress through the following steps:

  1. Spot Utility Repair
  2. Curb and Gutter Repairs, ADA Curb Ramp Installation /li>
  3. Milling of Existing Asphalt
  4. Asphalt Overlay

Due to the number of neighborhoods where work occurs and number of contractors involved, there may be time between each phase because of the complexity of the project. We appreciate your patience and cooperation throughout the whole process.

Routine maintenance is the key to managing our street assets in a cost-effective manner. Well-timed maintenance (i.e., crack sealing, surface treatment, and mill and overlay) allow streets to stay in good condition and extend the life of the street. Here are some of the reasons we mill and overlay streets:

  • It is a cost-effective way to extend the life of a street. The new asphalt not only seals the street, but also provides some structural value.
  • Milling removes deterioration and helps to restore the street to its original shape.
  • Other needed improvements (i.e., sanitary sewer and concrete repairs) can efficiently be made in conjunction with this program. This allows for multiple benefits to the City’s infrastructure through the implementation of this program.
  • Although construction can be inconvenient at times, this program is far less invasive than a street reconstruction project.
  • The end product is aesthetically appealing, improves the ride, and extends the life of the street. 

Milling consists of grinding the top surface of the asphalt down approximately 2 inches to make room for a new layer of asphalt. The byproduct of this operation is a material known as ‟millings.” Millings can be reused in place of gravel in street construction or can be recycled at the asphalt plant to make new asphalt. The asphalt overlay takes place in the days following the milling operation.

You can drive on the street after it has been milled. The asphalt overlay will happen shortly after the street has been milled.

After we overlay a street, we have to close the street afterwards for a short period of time. Depending on air temperature, the street may remain closed for four to eight hours while the asphalt cools down. Barricades will be removed from the street when crews have determined the street is ready to be opened. Please continue to be patient and do not drive around barricades to access a street under construction.

After paving, asphalt can still be above 200°F. At this temperature, the new asphalt can be damaged by vehicles and people. Even when the street is back open to traffic, the new asphalt still may be susceptible to damage. In the first few days after paving, please avoid turning your tires while stopped to prevent the surface from tearing or scaring.

Sign Up for Notifications

Contact Information

Curb Repairs or Seeding
Nick Traupel (7,8,10,12,&15)
ntraupel@siouxfalls.org
(605) 367-8661

Sayre Associates
Doug Hoy (Areas 9,11,14,&16) 
dough@sayreassociates.com
(605) 940-1055

Utility Work
Nagwan Al Janabi
naljanabi@siouxfalls.org
(605) 367-8643

Asphalt Paving Schedule
Cammy Larson
clarson@siouxfalls.org
(605) 367-8255