Project Update

Project Update

The project team held a public meeting on January 31, 2013, to present the new alternative to the public. Links to the information presented are in the Public Outreach section below.


January Project Update
Rail Yard Redev

Downtown Sioux Falls Rail Yard Redevelopment

Welcome to the City of Sioux Falls’ website for the Downtown Sioux Falls Rail Yard Redevelopment Project. This site is the source for information related to the study of alternatives and public involvement. We encourage you to review the project materials and offer your comments, suggestions and input via our e-comment form found in the Feedback section.
Environmental Assessment

Environmental Assessment

The Environmental Assessment document will be posted on the webpage once it is completed and ready for public review and comment.
FAQ

Frequently Asked Questions

The Frequently Asked Questions document is being revised based on comments received at the public meeting. Check back in June for an updated FAQ.


Feedback

Feedback

Submit questions or comments with the feedback form below.
Feedback
 

Objective

To assess the feasibility of removing the rail yard out of downtown and determine options for its relocation. This would then create a redevelopment opportunity in the core part of downtown.


Project Milestones

Develop details on new alternative  Sept. 2012
Update Project Management Plan  Sept. 2012
Revise MOU  Sept. 2012
SHPO and Section 4(f)  Sept. 2012—April 2013
Drafting Preliminary EA  Oct. 2012—Jan. 2013
Hold Public Meeting  Jan. 31, 2013
Draft EA Completed  June 2013
Hold Public Meeting  June 2013
Final EA Completed  August 2013
Rail Yard Purchase  Dec. 2013

 

 