Objective
To assess the feasibility of removing the rail yard out of downtown and determine options for its relocation. This would then create a redevelopment opportunity in the core part of downtown.
Project Milestones
| Develop details on new alternative |
Sept. 2012 |
| Update Project Management Plan |
Sept. 2012 |
| Revise MOU |
Sept. 2012 |
| SHPO and Section 4(f) |
Sept. 2012—April 2013 |
| Drafting Preliminary EA |
Oct. 2012—Jan. 2013 |
| Hold Public Meeting |
Jan. 31, 2013 |
| Draft EA Completed |
June 2013 |
| Hold Public Meeting |
June 2013 |
| Final EA Completed |
August 2013 |
| Rail Yard Purchase |
Dec. 2013 |