12th Street – Summit Avenue to Grange Avenue

Project Update 7/31/2020

  • Electrical contractors are working on new street light bases right now and should have new light poles up in the next two weeks.
  • The contractor is currently paving Phase 2. 
  • They will be placing black dirt behind the curb Friday this week and will be seeding Monday next week. 
  • Traffic will be open to Phase 2 by the middle of next week.

Project Milestones

Phase 1:

  1. Removal of existing surfacing
  2. Sanitary sewer installation
  3. Storm drainage repairs
  4. Water main installation
  5. Grading and gravelling
  6. Concrete work
  7. Street light improvements
  8. Paving
     

Phase 2:

  1. Removal of existing surfacing
  2. Sanitary sewer installation
  3. Storm drainage repairs
  4. Water main installation
  5. Grading and gravelling
  6. Concrete work
  7. Street light improvements
  8. Paving

Commuter Route Information:

  • 12th Street is currently closed between Walts Avenue and Summit Avenue. 
  • The intersection of 12th Street and Prairie Avenue is closed.
     
 

Sign Up for Notifications

Project Overview

Estimated Completion Date:

60 Working Days and by November 6, 2020

Contract Amount:

$964,977.38 

Project Summary:

This project will reconstruct 12th Street between Summit Avenue and Grange Avenue due to the deteriorated condition of the pavement and underground utilities.  Improvements will include new water main, sanitary sewer, storm drainage repairs, street light improvements, new accessible curb ramps, curb and gutter, and asphalt surfacing. 

Contact Information

City of Sioux Falls

Kari Johnson, Project Manager
kjohnson@siouxfalls.org
605-367-8611, (office)
605-777-2859 (cell)

Consultant Name:

Sayre Associates
Zach Kiesow
zachk@sayreassociates.com 
605-332-7211 (office) 
605-370-1948 (cell)

Contractor Name

Asphalt Surfacing Company