12th Street – Summit Avenue to Grange Avenue

Project Update 8/14/2020

  • Traffic is open in both Phase 1 and Phase 2.  
  • Electrical contractors are working on new street light bases in Phase 2 right now and should have new light poles up in the next week.
  • This will be the last webpage update, thanks for your cooperation during this project!

Project Milestones

Phase 1:

  1. Removal of existing surfacing
  2. Sanitary sewer installation
  3. Storm drainage repairs
  4. Water main installation
  5. Grading and gravelling
  6. Concrete work
  7. Street light improvements
  8. Paving
     

Phase 2:

  1. Removal of existing surfacing
  2. Sanitary sewer installation
  3. Storm drainage repairs
  4. Water main installation
  5. Grading and gravelling
  6. Concrete work
  7. Street light improvements
  8. Paving

Commuter Route Information:

  • 12th Street is open to traffic!12th Street is open to traffic!
     
 

Sign Up for Notifications

Project Overview

Estimated Completion Date:

60 Working Days and by November 6, 2020

Contract Amount:

$964,977.38 

Project Summary:

This project will reconstruct 12th Street between Summit Avenue and Grange Avenue due to the deteriorated condition of the pavement and underground utilities.  Improvements will include new water main, sanitary sewer, storm drainage repairs, street light improvements, new accessible curb ramps, curb and gutter, and asphalt surfacing. 

Contact Information

City of Sioux Falls

Kari Johnson, Project Manager
kjohnson@siouxfalls.org
605-367-8611, (office)
605-777-2859 (cell)

Consultant Name:

Sayre Associates
Zach Kiesow
zachk@sayreassociates.com 
605-332-7211 (office) 
605-370-1948 (cell)

Contractor Name

Asphalt Surfacing Company