12th Street – Summit Avenue to Grange Avenue
Project Update 8/14/2020
- Traffic is open in both Phase 1 and Phase 2.
- Electrical contractors are working on new street light bases in Phase 2 right now and should have new light poles up in the next week.
- This will be the last webpage update, thanks for your cooperation during this project!
Project Milestones
Phase 1:
- Removal of existing surfacing
- Sanitary sewer installation
- Storm drainage repairs
- Water main installation
- Grading and gravelling
- Concrete work
- Street light improvements
- Paving
Phase 2:
- Removal of existing surfacing
- Sanitary sewer installation
- Storm drainage repairs
- Water main installation
- Grading and gravelling
- Concrete work
- Street light improvements
- Paving
Commuter Route Information:
- 12th Street is open to traffic!12th Street is open to traffic!
Sign Up for Notifications
Project Overview
Estimated Completion Date:
60 Working Days and by November 6, 2020Contract Amount:
$964,977.38Project Summary:
This project will reconstruct 12th Street between Summit Avenue and Grange Avenue due to the deteriorated condition of the pavement and underground utilities. Improvements will include new water main, sanitary sewer, storm drainage repairs, street light improvements, new accessible curb ramps, curb and gutter, and asphalt surfacing.Contact Information
City of Sioux Falls
Kari Johnson, Project Managerkjohnson@siouxfalls.org
605-367-8611, (office)
605-777-2859 (cell)
Consultant Name:
Sayre AssociatesZach Kiesow
zachk@sayreassociates.com
605-332-7211 (office)
605-370-1948 (cell)
Contractor Name
Asphalt Surfacing Company