2023 ADA Accessibility Improvements
Project Update 7/28/2023
- Final landscaping work is underway and the project will be fully complete in early August.
- This will be the final update for this project.
Commuter Route Information:
- The outside eastbound lane of 41st Street is closed between Grange Avenue and Spring Avenue until the project is complete in early August.
Project Milestones
- North side of 41st Street between Minnesota Avenue and Grange Avenue.
- North side of 41st Street between Grange Avenue and Willow Avenue.
- South side of 41st Street between Willow Avenue and Grange Avenue.
- South side of 41st Street between Grange Avenue and Spring Avenue.
Project Overview
Completion Date:
July 2023
Contract Amount:
$879,271
Project Summary:
This project consists of ADA Accessibility Improvements along 41st Street between Willow Avenue and Minnesota Avenue. Work will include reconstruction of accessible curb ramps, landings, fillet sections, sidewalks with corresponding driveway restorations, and concrete curb and gutter repairs.
Contact Information
City of Sioux Falls
Tallon Cazer
tcazer@siouxfalls.org
(605)367-8609
Consultant Name:
JSA Engineers and Land Surveyors
Travis Clark
travis@jsaengineers.biz
(605)367-1036
Contractor Name:
Black-Top Paving Company