57th street Expansion Project from Veterans Parkway to Sparta Avenue

Project Update 9/1/2023    

  • Mainline paving along 57th street has been completed.
  • Contractor is working on installing sidewalk and median along 57th street from Veterans Parkway to Sparta Avenue. 

Commuter Route Information:  

  • 57th street from Veterans Parkway to Six Mile Road will be closed to through traffic.
  • Access to local residents only.

Project Milestones

  1. Road Closed
  2. Removals
  3. Sanitary sewer
  4. Watermain
  5. Storm Sewer
  6. Grading
  7. Subgrade Stabilization
  8. Gravelling
  9. Curb and Gutter
  10. Concrete Surfacing
  11. Sidewalk 
  12. Median
  13. Restoration
  14. Open to Traffic
     

57th Street at Linedrive facing West

57h St. at Sparta Avenue Southeast fillet

57th St. at Sparta Avenue Southwest fillet

57th St. facing east

57th Street facing West

57th Street facing West at Faith Avenue

57th Street facing West at Line Drive

Project-Overlay

Completion Date:

October 2023

Contract Amount: 

$5,514,424.02 

Project Summary:

This project consists of grading, utility, and surfacing construction of 57th street from Veterans Parkway to Six Mile Road. 

Contact Information

City of Sioux Falls
Vish Nellore
vnellore@siouxfalls.org
605-367-8643

Consultant Name:

JSA Engineers and Land Surveyors
travis@jsaengineers.biz
605-367-1036

Contractor Name:

T&R Contracting