66th Street Water Main Improvements

Project Update 9/16/2021 

  • The contractor continues to install watermain in phase 3.
  • We anticipate that the watermain work will be completed in approximately 2 weeks, weather permitting.

Project Milestones 

  1. Phase 1 (66th & Sundowner)
  2. Phase 2
  3. Phase 3
  4. Phase 4
  5. Phase 5
  6. Phase 6 (Mill and Overlay all Phases)

Commuter Route Information: 

  • 66th Street is closed to resident traffic in the phase 3 work area.
  • Residents in the phase 3 work area will not have access to their driveways for the duration of the phase.
  • Upon the completion of the work in phase 3 residents will be allowed to access their driveways while the work moves to the next phase.

66th Street Exhibit

Project Overview

Completion Date:

Mid-November, 2021

Contract Amount: 

$1,178,425.81  

Project Summary:

This project consists of water main improvements along 66th Street and Jordan Court from Sundowner Avenue to Holbrook Avenue, Alex Court, and Holbrook Avenue from Jordan Court to 66th Street due to the deteriorated condition of the water main.  The City is exploring either lining the existing water main, or replacing the water main.  The exact scope of work will vary depending on which method is selected.

Contact Information

City of Sioux Falls
Vish Nellore
vnellore@siouxfalls.org
605-367-8643

Consultant Name:

Ulteig Engineers, Inc.
Project Engineer:
Chad Stensland 
chad.stensland@ulteig.com
Office: 605 323 6022  
Cell: 605 359 7779

Contractor Name:

First Rate Excavate, Inc.