69th Street & Sycamore Avenue Improvements

Exhibit

Download Exhibit 

Project Update 6/18/2021 

  • The contractor has completed the underground utility work.
  • The contractor will be working on grading and gravelling on the project over the next few weeks.

Commuter Route Information: 

  • 69th Street is closed from Bahnson Avenue through Sycamore Avenue.
  • Sycamore Avenue is closed from Graystone Avenue through the intersection of 69th Street. 

Project Milestones 

  1. Traffic Control and Erosion Control
  2. Private Utility Relocation
  3. Storm Drainage
  4. Sanitary Sewer
  5. Watermain
  6. Grading
  7. Gravel
  8. Curb & Gutter
  9. Other Concrete Work
  10. Asphalt Paving
  11. Street Lighting
  12. Signs and Striping
  13. Seeding/Restoration
     

Project Overview

Completion Date:

October 22, 2021

Contract Amount: 

$2,707,253.90  

Project Summary:

This project consists of grading, utility, and surfacing construction on 69th Street (from 500’ East of Bahnson Avenue to 670’ East of Sycamore Avenue) and on Sycamore Avenue (from 500’ North of 69th Street to the Intersection of 69th and Sycamore). Underground utility work will include sanitary sewer, watermain, and storm sewer. Surfacing will include geofabric and aggregate base course, concrete curb & gutter, asphalt pavement, concrete sidewalk, pavement marking, lighting, traffic conduit, and permanent signing. Private utility companies will also be upgrading and relocating their facilities during the project.  This project is development driven to meet the traffic needs in the area.

Contact Information

City of Sioux Falls
Tallon Cazer
(605)367-8609
tcazer@siouxfalls.org

Consultant Name:

JSA Engineers
Travis Clark
(605)359-5450
travis@jsaengineers.biz

Contractor Name:

Prunty Construction