6th Street Bridge

Project Update 1/26/2023  

  • Public Open House is scheduled for January 31, 2023 from 4-6 p.m. at the Downtown Library, 200 N Dakota Ave.
  • 6th Street closure for bridge demolition planned to begin early-February.

Commuter Route Information: 

  • 6th Street is currently open to traffic.
  • 6th Street and bike trail underneath the bridge will be fully closed to vehicles and pedestrians once construction begins construction.
  • Access to LSS and Cherapa II will be maintained via 6th Street from Weber Ave.

2023

  1. Street Closure; Removals
  2. Bridge Construction
  3. Surfacing/Paving
  4. Street Lights, Sidewalk, Streetscape
  5. Site Restoration
     

Project Overview

Completion Date:

2024

Contract Amount: 

$21,821,916.09

Project Summary:

The City of Sioux Falls will be reconstructing 6th Street from the Big Sioux River to Weber Ave, including bridge, roadway, and underground utility improvements.

Contact Information

City of Sioux Falls
Wes Philips
wphilips@siouxfalls.org
605-367-8657

Consultant Name:

Infrastructure Design Group
Project Engineer:
Phil Gundvaldson
philg@infrastructuredg.com
605-271-5527

Contractor Name:

SFC Civil Constructors/Journey Group