Project Update 4/29/2022
- Project is rescheduled for the 2023 construction season due to supply chain challenges and escalating costs experienced throughout our region.
Commuter Route Information:
(no changes)
- 7th Street east of Phillips Avenue will be fully closed to vehicles and pedestrians during construction.
- Access to adjacent properties will be maintained.
Project Milestones
2023
- Removals
- Utility Repair and Reconstruction
- Grading and Gravel
- Surfacing/Paving
- Street Lights, Sidewalk, Streetscape
- Site Restoration
Sign up for Project Updates
Project Overview
Completion Date:
Fall 2023
Contract Amount:
TBD
Project Summary:
The City of Sioux Falls will be reconstructing the 7th Street cul-de-sac east of Phillips Avenue. The project will include replacement of underground utilities, street surfacing, streetscape and a new pedestrian connection to the Arc of Dreams.
Contact Information
City of Sioux Falls
Wes Philips
wphilips@siouxfalls.org
605-367-8657
Constultant
Infrastructure Design Group
Project Engineer:
Chad Hanisch
ChadH@infrastructuredg.com
605-271-5527
Contractor Name:
TBD