Cliff Avenue Rehabilitation from East 26th Street to East Pam Road
Download Cliff Avenue Project Phasing
Project Update 9/15/2022
-
The project is complete.
Commuter Route Information:
-
The project is complete with all lanes of traffic on Cliff Avenue from 26th Street to East Pam Road open.
Project Milestones
Phase 1: Cliff Avenue southbound driving lanes between 26th Street and Pam Road
- Curb & gutter and fillet repairs.
- PCC panel and joint repairs.
- Partial depth pavement repairs.
- Accessible sidewalk repairs.
- Topsoil Placement
- Pavement Markings
Phase 2: Cliff Avenue northbound driving lanes between Pam Road and 26th Street
- Curb & gutter and fillet repairs.
- PCC panel and joint repairs.
- Partial depth pavement repairs.
- Accessible sidewalk repairs.
- Topsoil Placement
- Pavement Markings
Phase 3: Cliff Avenue center turn lane from 33rd Street to Pam Road
- Curb & gutter and fillet repairs.
- PCC panel and joint repairs.
- Partial depth pavement repairs.
- Accessible sidewalk repairs.
- Topsoil Placement
- Pavement Markings
Phase 4: East 26th Street intersection
- Curb & gutter and fillet repairs.
- PCC panel and joint repairs.
- Partial depth pavement repairs.
- Accessible sidewalk repairs.
- Topsoil Placement
- Pavement Markings
Phase 5: East 33rd Street intersection
- Curb & gutter and fillet repairs.
- PCC panel and joint repairs.
- Partial depth pavement repairs.
- Accessible sidewalk repairs.
- Topsoil Placement
- Pavement Markings
Project Overview
Completion Date:
August 13, 2022
Contract Amount:
$2,921,000.00
Project Summary:
This project will rehabilitate Cliff Avenue between East 26th Street and East Pam Road. Work will include full depth concrete patching, partial depth concrete patching, curb and gutter repair, sidewalk accessible curb ramp replacement, and pavement markings. This project will also update the pedestrian push buttons to accessible pedestrian signal push buttons. These APS buttons use audible tones to communicate when a pedestrian should cross the street.
Contact Information
City of Sioux Falls
Michell Knoll
mknoll@siouxfalls.org
605-367-8632
Consultant Name:
Marshall Engineering Inc.
Marshall Runge, PE
marshall.marshalleng@midconetwork.com
605-940-0343
Contractor Name:
Dakota Contracting Corporation