E. 6th Street Concrete Rehabilitation and Asphalt Overlay from I-229 to N. Sycamore Avenue

 

Project Map

Project Update 9/1/2023    

  • Phase 1 and Phase 2:  The permanent pavement markings have been applied and this portion of the project is complete and fully open to traffic.
  • Concrete repairs are complete in the westbound lanes between Sycamore and Linwood Court.
  • The contractor is working on the partial depth concrete repairs, full depth concrete repairs, and curb & gutter repairs in the eastbound lanes, between Linwood Court and Sycamore Avenue.

Looking Ahead:

  • When concrete repairs have been completed in the eastbound lanes, the contractor will proceed to Phase 3C where they will pick up a few repairs that are located on the centerline of the street between Linwood Court and Sycamore Avenue.  Work will then progress to concrete repairs in Phase 4, the area between east end of asphalt overlay to Linwood Court.
  • After all concrete repairs have been made, the grinding contractor will begin diamond grinding the finished concrete pavement to provide a smooth and uniform driving surface. 

Commuter Route Information:  

  • The eastbound lanes are closed between Linwood Court and Sycamore Avenue.
  • At a minimum, one lane of traffic will always remain open in all directions.
  • Access to businesses, parks and schools will be maintained. Access to side streets will be maintained if possible.

Project Milestones

Phase 1

Phase 1:  Outside lanes - E. 6th Street from I-229 to 1300 feet east of the Cleveland Avenue Intersection and the outside lanes of Cleveland Avenue, 650 feet north and south of the 6th Street intersection. 

  1. Curb & gutter and fillet repairs
  2. ADA sidewalk ramp upgrades
  3. Mill concrete surface
  4. Asphalt overlay
  5. Seeding & topsoil placement
  6. Pavement Markings

   

Phase 2

Phase 2:  Inside lanes - E. 6th Street from I-229 to 1300 feet east of the Cleveland Avenue Intersection and the outside lanes of Cleveland Avenue, 650 feet north and south of the 6th Street intersection. 

  1. Asphalt overlay
  2. Pavement Markings

Phase 3A

Phase 3A:  Westbound lanes - E. 6th Street from approximately Linwood Court to west of Sycamore Avenue.

  1. Curb & gutter and fillet repairs
  2. Full depth concrete panel and joint repairs
  3. Partial depth concrete pavement repairs
  4. ADA sidewalk ramp upgrades 
  5. Seeding & topsoil placement

Phase 3B

Phase 3B:  Eastbound lanes - E. 6th Street from approximately Linwood Court to west of Sycamore Avenue.

  1. Curb & gutter and fillet repairs
  2. Full depth concrete panel and joint repairs
  3. Partial depth concrete pavement repairs
  4. ADA sidewalk ramp upgrades 
  5. Seeding & topsoil placement

Curb removal looking West on 6th St.

Beginning to crush the curb for removal on 6th St.

Grooving for permanent pavement markings.

Partial depth repairs on. 6th by Washington High School.

 

Phase 3C

Phase 3C:  Inside lanes - E. 6th Street from approximately Linwood Court to west of Sycamore Avenue.

  1. Full depth concrete panel and joint repairs
  2. Partial depth concrete pavement repairs

Phase 4A

Phase 4A:  Westbound lanes - E. 6th Street from 1300 feet east of the Cleveland Avenue Intersection to approximately Linwood Court.

  1. Curb & gutter and fillet repairs
  2. Full depth concrete panel and joint repairs
  3. Partial depth concrete pavement repairs
  4. ADA sidewalk ramp upgrades 
  5. Seeding & topsoil placement

Phase 4B

Phase 4B:  Eastbound lanes - E. 6th Street from 1300 feet east of the Cleveland Avenue Intersection to approximately Linwood Court.

  1. Curb & gutter and fillet repairs
  2. Full depth concrete panel and joint repairs
  3. Partial depth concrete pavement repairs
  4. ADA sidewalk ramp upgrades 
  5. Seeding & topsoil placement

Phase 4C

Phase 4C:  Inside lanes - E. 6th Street from 1300 feet east of the Cleveland Avenue Intersection to approximately Linwood Court.

  1. Full depth concrete panel and joint repairs
  2. Partial depth concrete pavement repairs

Phase 5

Phase 5:  All lanes - E. 6th Street from 1300 feet east of the Cleveland Avenue Intersection to west of Sycamore Avenue.

  1. Diamond grinding of concrete pavement surface
  2. Reseal concrete pavement joints
  3. Pavement Markings
     

Project Overview

Completion Date:

October 2023

Contract Amount: 

$3,564,585.57

Project Summary:

This project will rehabilitate East 6th Street between I-229 to North Sycamore Avenue.  Work will include full depth concrete patching, partial depth concrete patching, curb and gutter repair, sidewalk ADA ramp replacement and diamond grinding of the finished pavement to provide a smooth and uniform driving surface. Due to the deteriorated condition of the existing concrete pavement, the area of 6th Street from I-229 to approximately Shepherd Avenue, including the intersection of Cleveland Avenue, will receive an asphalt overlay.

Contact Information

City of Sioux Falls
Michell Knoll
605-367-8632
mknoll@siouxfalls.org

Consultant Name:

Marshall Engineering Inc.
Marshall Runge 
605-940-0343
marshall.marshalleng@midconetwork.com

Contractor Name:

Dakota Contracting Corporation