Highland Addition Improvements – Phase 3

Highland

Project Update 10/21/2022  

  • Phase 1: Sherman Avenue 3rd to 4th St re-construction has been completed and the street is open to the residents and to the public. 
  • Phase 2: Sherman Avenue from 5th Street to 6th Street re-construction has been completed and the street is open to the residents and to the public. 
  • Phase 3: Wayland Avenue from 5th Street to 6th Street re-construction has been completed and the street is open to the residents and the public
  • This is the Last Webpage Update as construction is complete and the contractor will be working on punch list items. 

Commuter Route Information: 

  • Sherman Avenue is open to traffic from 3rd St to 4th St
    Residents have vehicle access to their residences as construction is complete.
    Sidewalks are accessible. 

  • Sherman Avenue is open to traffic from 5th St to 6th St
    Residents have vehicle access to their residences as construction is complete.
    Sidewalks are accessible.  

  • Wayland Avenue is open to traffic from 5th St to 6th St
    Residents have vehicle access to their residences as construction is complete. 
    Sidewalks are accessible. 

Project Milestones 

Phase 1: Sherman Avenue from 3rd Street to 4th Street

  1. Removals
  2. Watermain installation
  3. Sanitary sewer installation
  4. Grading
  5. Subgrade stabilization
  6. Gravelling
  7. Paving
  8. Restoration

Phase 2:Sherman Avenue from 5th Street to 6th Street

  1. Removals
  2. Watermain installation
  3. Sanitary sewer installation
  4. Grading
  5. Subgrade stabilization
  6. Gravelling
  7. Paving
  8. Restoration

Phase 3: Wayland Avenue form 5th Street to 6th Street

  1. Removals
  2. Watermain installation
  3. Sanitary sewer installation
  4. Grading
  5. Subgrade stabilization
  6. Gravelling
  7. Paving
  8. Restoration

Project Overview

Completion Date:

Fall 2022

Contract Amount: 

$811,147.59  

Project Summary:

The project will reconstruct Sherman Avenue from 3rd Street to 4th Street, Sherman Avenue from 5th Street to 6th Street, and Wayland Avenue from 5th Street to 6th Street. Improvements will include the removal and replacement of the curb & gutter, asphalt pavement, sanitary sewer, and watermain. 

Contact Information

City of Sioux Falls
John Osman
josman@siouxfalls.org 
605-367-8601

Consultant Name:

Ulteig Engineers, Inc.
Project Engineer:
Chad Stensland 
chad.stensland@ulteig.com
Office: 605 323 6022  
Cell: 605 359 7779

On Site Representative: 
Enock Ariko
Email:  enock.ariko@ulteig.com
Office:  (605) 323-6054
Cell:  712-578-1975

Contractor Name:

H & W Contracting, LLC