2019 Kingswood Way Drainage Improvements

Kingswood

Project Update: 10/25/2019

  • The contractor has completed the asphalt paving for the entire project. 
  • Site restoration will follow in the next week or two. 
  • Street light installation will occur as soon as they are delivered from the manufacturer. 
  • This will be the last project update for this project.

Project Milestones

Phase 1A

32nd Street - Karen Drive to Royal Court

  1. Remove existing street section
  2. Install Storm Drainage Pipe
  3. Install Water Main
  4. Replace curb and gutter
  5. Replace Sidewalk and Accessible Curb Ramps
  6. Replace street surfacing

Phase 1B

Kingswood Way - 32nd Street to Walden Drive:

  1. Remove existing street section
  2. Install Storm Drainage Pipe
  3. Install Water Main
  4. Replace curb and gutter
  5. Replace Sidewalk and Accessible Curb Ramps
  6. Replace street surfacing

Phase 2

Kingswood Way - Walden Drive to 36th Street; 36th Street - Steven Drive to Gibson Avenue; and Steven Drive - 36th Street to 37th Street: 

  1. Remove existing street section
  2. Install Storm Drainage Pipe
  3. Install Water Main
  4. Replace curb and gutter
  5. Replace Sidewalk and Accessible Curb Ramps
  6. Replace street surfacing
     

Commuter Route Information

  • Kingswood Way is now open to traffic. 
  • Use care when driving in the neighborhood because site restoration and street light installation will be ongoing.
     

Sign Up for Notifications

Project Overview

Estimated Completion Date:

Start on or after April 29; Complete within 85 Working Days and by October 1, 2019; Seeding complete by November 15, 2019 

Contract Amount:

$1,267,648.15 

Project Summary:

This project will reconstruct Steven Drive from 37th Street to 36th Street; 36th Street from Steven Drive to Kingswood Way; and Kingswood Way from 36th Street to 32nd Street. Work includes installation of new storm drainage pipe, water main repairs, partial replacement of curb and gutter, new accessible curb ramps, street light improvements, and new asphalt surfacing. 

Contact Information

City of Sioux Falls

Tim Krueger, Project Manager
tkrueger@siouxfalls.org 
605-367-8615 (office)
605-940-5280 (cell)

Consultant Name:

Banner Associates, Inc.
Kent R. Johnson, PE, CFM |
kentj@bannerassociates.com
Banner Associates, Inc. | Sioux Falls, SD
Toll Free | 1.855.323.6342 x 3238
Cell | 1.605.695.0921

Alex Welbig
Banner Associates, Inc.
alexw@bannerassociates.com
1-855-323-6342
605-261-8212

Contractor Name

Winter Brothers Underground, Inc.