2019 Kingswood Way Drainage Improvements

Kingswood

Project Update: 06/07/2019

Contractor has completed the utility work on 32nd Street and will begin grading for curb and gutter, sidewalk and accessible curb ramps, and street surfacing. Water Main and Storm Sewer have been installed on Kingswood Way to Chadwick Place. Work will continue with Storm Sewer installation to the south along Kingswood Way.

Project Milestones

Phase 1A

32nd Street - Karen Drive to Royal Court

  1. Remove existing street section
  2. Install Storm Drainage Pipe
  3. Install Water Main
  4. Replace curb and gutter
  5. Replace Sidewalk and Accessible Curb Ramps
  6. Replace street surfacing

Phase 1B

Kingswood Way - 32nd Street to Walden Drive:

  1. Remove existing street section
  2. Install Storm Drainage Pipe
  3. Install Water Main
  4. Replace curb and gutter
  5. Replace Sidewalk and Accessible Curb Ramps
  6. Replace street surfacing

Phase 2

Kingswood Way - Walden Drive to 36th Street; 36th Street - Steven Drive to Gibson Avenue; and Steven Drive - 36th Street to 37th Street: 

  1. Remove existing street section
  2. Install Storm Drainage Pipe
  3. Install Water Main
  4. Replace curb and gutter
  5. Replace Sidewalk and Accessible Curb Ramps
  6. Replace street surfacing
     

Commuter Route Information

Phase 1A: 32nd Street is closed between Karen Drive and Royal Court.  Traffic is being detoured to 26th Street and 36th Street.
Phase 1B: 
Kingswood Way is closed between 32nd Street and Walden Drive.
Phase 2:
Kingswood Way is open south of Walden Drive. 

 
 

Sign Up for Notifications

Project Overview

Estimated Completion Date:

Start on or after April 29; Complete within 85 Working Days and by October 1, 2019; Seeding complete by November 15, 2019 

Contract Amount:

$1,267,648.15 

Project Summary:

This project will reconstruct Steven Drive from 37th Street to 36th Street; 36th Street from Steven Drive to Kingswood Way; and Kingswood Way from 36th Street to 32nd Street. Work includes installation of new storm drainage pipe, water main repairs, partial replacement of curb and gutter, new accessible curb ramps, street light improvements, and new asphalt surfacing. 

Contact Information

City of Sioux Falls

Tim Krueger, Project Manager
tkrueger@siouxfalls.org 
605-367-8615 (office)
605-940-5280 (cell)

Consultant Name:

Banner Associates, Inc.
Joe Munson, PE
Banner Associates, Inc.
joem@bannerassociates.com
1-855-323-6342
605-941-4276

Alex Welbig
Banner Associates, Inc.
alexw@bannerassociates.com
1-855-323-6342
605-261-8212

Contractor Name

Winter Brothers Underground, Inc.