41st Street Water Transmission Line Rehabilitation

Project Update 8/5/2022  

  • Road restoration for Phase 1 continues.
  • Work in Phase 1 is planned to be complete at the beginning of next week.
  • Pipe bursting for Phase 2 continues.

Commuter Route Information: 

  • The eastbound lanes of 41st Street from Sertoma Ave to Kuehn Park Road are closed. 
  • Eastbound traffic will utilize the center turn lane. 
  • The south leg of the intersection of 41st Street and Kuehn Park Road is closed.
  • Valley View Road/Holbrook Avenue is closed for northbound and southbound traffic.
  • Eastbound and westbound traffic can turn north onto Valley View Road.
  • Access to businesses/apartment buildings will be maintained.

Project Milestones 

Phase 1

  1. Excavation at access pit locations
  2. Watermain rehabilitation
  3. Fill and pave access pits

Phase 2

  1. Excavation at access pit locations
  2. Watermain rehabilitation
  3. Fill and pave access pits

Phase 3

  1. Excavation at access pit locations
  2. Watermain rehabilitation
  3. Fill and pave access pits

 

Project Overview

Completion Date:

Phase 3 completed in 2021.
Phase 1 and 2 expected completion in summer 2022.

Contract Amount: 

$2,440,000

Project Summary:

This project will consist of rehabilitation of the existing 16” diameter and 20” diameter water transmission mains along 41st Street from Sertoma Avenue to Marion Road. Access pits will be excavated periodically throughout the project limits. Work will include rehabilitation of these water transmission mains via trenchless construction methods and restoration of all surfacing at each pit location.

Contact Information

City of Sioux Falls
Nick Rezac
605-367-8665
Email: nrezac@siouxfalls.org

Consultant Name:

Banner Associates
Joe Munson
(605) 941-4276
joem@bannerassociates.com

Alex Welbig
(605) 261-8212
alexw@bannerassociates.com

Contractor Name:

Site Works