Marion Road from Madison Street to Maple Street Improvements

Project Update: 10/27/2020 

  • Placement of concrete surfacing on Marion Road is complete.
  • Installation of lighting along Marion Road is nearing completion. 
  • Sidewalk placement is continuing on the west side of Marion Road.
  • Topsoil placement in boulevard areas between W. Maple Street and W. Madison Street is ongoing. 
  • Landscaping work is expected to begin soon.
  • The project was opened to traffic on Friday, October 23, 2020. 
  • Various project work will continue for the next several weeks.

2020 Project Milestones

  1. Surfacing removal
  2. Grading
  3. Underground utility installation
  4. Fine grading and cement treated subgrade
  5. Graveling
  6. PCC pavement surfacing
  7. Roadway lighting & Traffic signals
  8. Sidewalk
  9. Topsoil & seeding

Commuter Route Information:

  • Marion Road between W. Maple Street and W. Madison Street is now open.
  • Expect various lane closures for the next few weeks as work continues near the edges of the roadway.
  • Please be aware of slow-moving construction traffic entering and exiting the work areas.

Detours

Marion Detour

Project Overvew

Completion Date:

October 24, 2020 with final cleanup by June 26, 2021

Contract Amount: 

$4.9 million

Project Summary:

Reconstruction of a rural asphalt pavement section to a four lane concrete pavement section with turning lanes.  Utility work includes traffic signals, street lights, storm sewer, sanitary sewer watermain.

Contact Infomation

City of Sioux Falls
John Osman
josman@siouxfalls.org
Office:  605 367 8640

Consultant Name:

Sayre Associates, Inc.
Scott Schnieder
scotts@sayreassociates.com
Office:  605 332 7211 
Cell:  605 940 1051  

Contractor Name:

T&R Contracting