Minnesota Avenue from Russell Street to 2nd Street
Project Update 11/11/2022
- Minnesota Avenue is now fully open to traffic.
- Temporary Street lighting in in place for the winter months.
- Beginning next spring, decorative lighting and street elements will be installed.
Commuter Route Information:
- All 4 lanes on Minnesota Avenue are open to traffic
Project Milestones
Phase 1A (west side of Minnesota Avenue, Russell Street to Bailey Street):
- Removals
- Water Main
- Sanitary Sewer
- Storm Drainage
- Grading
- Graveling
- Concrete Pavement
- Other Miscellaneous Concrete Work – sidewalks retaining walls, etc.
Phase 1B (west side of Minnesota Avenue, Bailey Street to 2nd Street):
- Removals
- Water Main
- Sanitary Sewer
- Storm Drainage
- Grading
- Gravelling
- Concrete Pavement
- Other Miscellaneous Concrete Work – sidewalks retaining walls, etc.
Phase 2 (east side of Minnesota Avenue):
- Removals
- Water Main
- Sanitary Sewer
- Storm Drainage
- Grading
- Gravelling
- Concrete Pavement
- Other Miscellaneous Concrete Work – sidewalks retaining walls, etc.
Phase3
- Median Construction
- Traffic Signals
- Street Lighting
- Site Restoration
Project Overview
Completion Date:
June 2023
Contract Amount:
$14,069,218.68
Project Summary:
This project consists of the complete reconstruction of Minnesota Avenue from Russell Street to 2nd Street. Work will include replacement of a 42” water main, a 12” watermain, and an 8” watermain; replacement of the sanitary sewer; storm drainage improvements; concrete pavement with a center median; enhanced pedestrian facilities, including new sidewalk, accent lighting, streetscaping, and bus stops; and installation of a new traffic signal at Brookings Street. Site restoration items, including landscaping and final seeding, will be completed in 2023.
Contact Information
City of Sioux Falls
Tim Krueger
tkrueger@siouxfalls.org
(605) 367-8615
Consultant Name:
HDR
Paul Sanow
paul.sanow@hdrinc.com
(605) 977-7756
Contractor Name:
T&R Contracting, Inc