Minnesota Avenue from Russell Street to 2nd Street

  • Project value$14,069,2108.68
  • Contractor nameT&R Contracting, Inc
  • Completion DateJune 30, 2023
Minnesota-Phasing 1

Project Update  7/3/2023 

  • Decorative lighting and street elements have been installed and are currently being programmed. 
  • This will be the final update as the programming is the last element of the project to be completed.

Commuter Route Information: 

  • All 4 lanes on Minnesota Avenue are open to traffic
  • Residents will be required to park on side streets as there is no longer on street parking along Minnesota Avenue.

Project Milestones 

Phase 1A (west side of Minnesota Avenue, Russell Street to Bailey Street):

  1. Removals
  2. Water Main
  3. Sanitary Sewer
  4. Storm Drainage
  5. Grading
  6. Graveling
  7. Concrete Pavement
  8. Other Miscellaneous Concrete Work – sidewalks retaining walls, etc.

Phase 1B (west side of Minnesota Avenue, Bailey Street to 2nd Street): 

  1. Removals
  2. Water Main
  3. Sanitary Sewer
  4. Storm Drainage
  5. Grading
  6. Gravelling
  7. Concrete Pavement
  8. Other Miscellaneous Concrete Work – sidewalks retaining walls, etc.

Phase 2 (east side of Minnesota Avenue): 

  1. Removals
  2. Water Main
  3. Sanitary Sewer
  4. Storm Drainage
  5. Grading
  6. Gravelling
  7. Concrete Pavement
  8. Other Miscellaneous Concrete Work – sidewalks retaining walls, etc.

Phase3

  1. Median Construction
  2. Traffic Signals
  3. Street Lighting
  4. Site Restoration