North Marion Road Improvements, 258th Street to Memory Lane
Project Update 9/7/2023
- Contractor continues road construction along North Marion Road.
- Phase 2 along MC Highway 130 will begin September 5th.
Commuter Route Information:
- Currently working through Phase 1 where North Marion Road will be closed.
- MC Highway 130 is closed.
Project Milestones
Phase 1 - Marion Road
- Removals
- Water Main
- Storm Drainage
- Grading
- Fabric & Gravel Placement
- Concrete Paving
- Pavement marking & permanent signing installation
- Lighting installation
- Restoration
Phase 2 - Minnehaha County Highway 130
- Removals
- Water Main
- Storm Drainage
- Grading
- Fabric & Gravel Placement
- Concrete Paving
- Pavement marking & permanent signing installation
- Lighting installation
- Restoration
Project Overview
Completion Date:
November 17, 2023
Contract Amount:
$3,079,038.47
Project Summary:
The City of Sioux Falls is partnering with Minnehaha County to reconstruct Marion Road between 258th Street (MC Hwy 130) and Memory Lane, as well as a portion of MC Hwy 130 due to the increased traffic from development in the area. Improvements include new water main, storm sewer, street lighting, concrete surfacing and asphalt surfacing.Contact Information
City of Sioux Falls
Dan Drake
ddrake@siouxfalls.org
605-367-8036 (office)
Consultant Name:
Sayre Associates, Inc.
Zach Kiesow
zachk@sayreassociates.com
605-332-7211 (office)
605-370-1948 (cell)
County Contact Information:
Jacob Maras
605-978-7044 (office)
605-759-0585 (cell)
Contractor Name:
D&G Concrete Construction, Inc.