Street Construction News

Lane Closure – 26th Street between Cambridge Avenue and Marion Road

Beginning on Monday morning, October 4, 2021, the Inside Westbound lane of West 26th Street will be closed between Cambridge Avenue and Marion Road for watermain maintenance work. Two lanes of traffic will be maintained in the eastbound lanes and one lane of traffic will be maintained in the westbound lane.

This is the fourth of five phases of work that will occur on 26th Street between Sertoma Avenue and Marion Road. Updates will be provided when traffic control is scheduled to change.

This work is anticipated to be complete by late October.

Drivers are urged to use caution and reduce their speed while travelling near the construction area and may want to consider alternate routes.

Lane Closure – 26th Street between Highland Avenue and Veterans Parkway

Beginning at 7 a.m. on Monday, October 4, 2021, the outside westbound lane of East 26th Street and the sidewalk on the north side of the road will be closed between Highline Avenue and Veterans Parkway. 

Journey Construction will be performing sidewalk replacement and road construction.

Weather permitting, this work is anticipated to be complete within one week.

Drivers are urged to use caution and reduced speeds while travelling near the construction area and may want to consider alternate routes.

Lane Closure – Cleveland Avenue

Beginning on Thursday morning, October 7, 2021, the southbound lane of North Cleveland Avenue will be closed between Pearl Street and Sixth Street. Southbound traffic will be shifted into the center turn lane to maintain two-way traffic.

Brooks Construction will be replacing the driveway approach at Brookshire Apartments.

Weather permitting, this work is anticipated to be complete by Friday, October 8, 2021.

Drivers are urged to use caution and reduced speeds while travelling near the construction area and may want to consider alternate routes.