Project Update 8/7/2020

  • Utility work and street grading are complete in Phase 1.
  • The contractor will be working on placing gravel, concrete repairs, and asphalt paving for the rest of this week and into next week.
  • The City has approved the contractor’s request to work on Phase 3 before Phase 2. 
  • Work will begin in Phase 3 late next week pending completion of Phase 1.

Project Milestones

Phase 1:

  1. Traffic Control and Erosion Control Installation
  2. Removal of Street Surfacing
  3. Installation of Water Main
  4. Installation of Storm Drainage Pipe
  5. Aggregate Base Course Placement
  6. Curb Ramp & Sidewalk Construction
  7. Asphalt Surfacing

Phase 2:

  1. Traffic Control and Erosion Control Installation<
  2. Removal of Street Surfacing
  3. Installation of Water Main
  4. Aggregate Base Course Placement
  5. Curb Ramp & Sidewalk Construction
  6. Asphalt Surfacing

Phase 3:

  1. Traffic Control and Erosion Control Installation
  2. Removal of Street Surfacing
  3. Installation of Water Main
  4. Aggregate Base Course Placement
  5. Curb Ramp & Sidewalk Construction
  6. Final Asphalt Surfacing
  7. Topsoil and Seeding

Commuter Route Information:

Phase 1: Drexel Drive –57th Street to Pebble Creek Road

  • Drexel Drive is closed between Pebble Creek Road and 57th Street.

Phase 2: Pebble Creek Road – Drexel Drive to Baneberry Drive

  • Pebble Creek Road will be closed to traffic between Drexel Drive and Baneberry Drive during this phase.

Phase 3: Pebble Creek Road – Holbrook Avenue to Drexel Drive

  • Once Phase 3 begins, Drexel Drive will reopen to traffic, and Pebble Creek Road will be closed between Holbrook Avenue and Drexel Drive.

Project Overview

Project Summary

This project consists of partial reconstruction of Pebble Creek Road from Holbrook Avenue to Baneberry Avenue, and partial reconstruction of Drexel Drive from 57th Street to Pebble Creek Road. Work will include replacement of the water main, a spot repair to the sanitary sewer main, a sanitary sewer manhole replacement, spot repairs to the curb and gutter, asphalt paving, asphalt mill and overlay of the non-water main side of the street, and upgrades to the accessible curb ramps.

Completion Date:

October 30, 2020

Contract Amount: 

$771,475.64

Contact Information

City of Sioux Falls
Josh VandenBos
jvandenbos@siouxfalls.org
605-367-8619

Consultant Name:

Short Elliot Hendrickson, Inc. (SEH)
Al Murra
amurra@sehinc.com
605-330-7015

Mike Czech
mczech@sehinc.com
507-215-3715

Contractor Name:

ASCO