  • The contractor will be working on installing curb, gutter and driveway approaches in phase one in the coming week.
  • Upgrades in the intersection of 18th St. will also continue.

Commuter Route Information: 

  • Phillips Ave. will be closed from the intersection of 18th St. north to the rail road tracks.
  • The intersection of 18th St. will also be closed.
  • Traffic will be detoured around the intersection of 18th St. via 22nd St. and 2nd Ave.    

Project Milestones

Phase 1 – Phillips Avenue – 18th Street to 200 feet North of Railroad Track

  1. Removals
  2. Sanitary Sewer
  3. Watermain
  4. Grading
  5. Gravelling
  6. Concrete Work
  7. Street Lights
  8. Asphalt Paving
  9. Site Restoration

Phase 2 – Phillips Avenue – 200 Feet North of Railroad Tracks to 14th Street

  1. Removals
  2. Sanitary Sewer
  3. Watermain
  4. Grading
  5. Gravelling
  6. Concrete Work
  7. Street Lights
  8. Asphalt Paving
  9. Site Restoration

Phase 3 – Intersection of 18th & Phillips

  1. Removals
  2. Sanitary Sewer
  3. Watermain
  4. Grading
  5. Gravelling
  6. Concrete Work
  7. Concrete Paving
  8. Site Restoration

Project Overview

Completion Date:

September 15, 2021

Contract Amount: 

$933,333.33 

Project Summary:

"This project will reconstruct Phillips Avenue from 14th Street to 18th Street due to the deteriorated condition of the underground utilities and street pavement. Improvements include new water main, sanitary sewer, street light improvements, new accessible curb ramps, curb and gutter, and asphalt surfacing.

Contact Information

City of Sioux Falls
Shane Balk
sbalk@siouxfalls.org 
605.367.8601

Consultant Name:

Ulteig Engineers, Inc.
Project Engineer:
Chad Stensland 
chad.stensland@ulteig.com
Office: 605 323 6022  
Cell: 605 359 7779

On Site Representative: 
Corey Maynard
corey.maynard@ulteig.com
Office: 605 323-6077  
Cell: 605 906-1531

Contractor Name:

T&R Contracting, Inc.