2020 Project Milestones

Phase 1A

  1. Installation of traffic control
  2. Miscellaneous surfacing removals
  3. Watermain installation
  4. Restoration

Phase 1B

  1. Installation of watermain through existing casing pipe under Interstate 90

Phase 2A

  1. Installation of traffic control and detour route
  2. Surfacing removals
  3. Watermain installation
  4. Restoration

Phase 2B

  1. Watermain installation
  2. Restoration

Phase 2C

  1. Installation of watermain through existing casing pipe under Interstate 29

Phase 2D

  1. Installation of traffic control
  2. Surfacing removals
  3. Watermain installation
  4. Restoration

Project Overview

Estimated Completion Date:

December 15, 2020

Contract Amount:

$1,500,000 (estimate)

Project Summary:

This project includes the installation of approximately 6600 feet (1.25 miles) of 16” water main connecting Kiwanis Avenue to Foundation Court. This will supply Foundation Park with a secondary source of water for redundancy, and provide access to City water for future development along Kiwanis Avenue.

Contact Information

City of Sioux Falls

Shane Balk
sbalk@siouxfalls.org
605-367-8608 

Consultant Name:

Stockwell Engineers
Ross Kuchta
rkuchta@stockwellengineers.com
605-338-6668

Contractor Name

SiteWorks