2023 Asphalt Overlay Program

Update: 6/1/2023 

  • Please view the map, dashboard, and tentative schedule found below. The schedule will be updated as we progress through the construction season. Finally, please sign up for email updates on the right side of the page and you will be notified by email when this webpage is updated.
  • For additional information that will provide up-to-date text information, please sign up at siouxfalls.org/alert. You will need to create an account so we can provide you with updated information such as when we mill, tack, pave, when equipment is down, or other delays.
  • Please see Frequent Asked Questions(FAQs) on the Overlay Program below and if you have additional questions, please contact one of the team members listed or email Mike Schmidt at MSchmidt3@SiouxFalls.org

Overlay Projects Map


Asphalt Mill & Overlay Status Dashboard

View Map in New Window

Overlay Program Schedule

Location Concrete Work  Utility Work  Asphalt Mill & Overlay 
1. Cliff Avenue: 11th Street to 26th Street Completed Completed Early June
2. Batcheller Lane Area: West of Minnesota Ave and North of 57th Street Completed
Completed
Mid-June
3. Rough Rider Area: West of Sertoma Between 41st and 32nd Street Completed
Completed Mid-June
4. Fireside Area: Northwest of 57th Street and Southeastern Ave Completed
Completed Early September
5. Marson Area: 49th Street to 41st Street from Bahnson to Southeastern  Completed
Completed Mid-July
6. Lewis Park Area: East of Cliff Ave Between 49th Street and 57th Street Completed
Completed Late September
7. Westport Area: East of Louise between 41st and 57th Street Completed
Completed Mid-May
8. Pettigrew Area: North of 10th Street Between West Ave and Minnesota Ave Completed
Completed Mid-August
9. Cathedral Area: North of 6th Street Between Minnesota Ave and West Ave Completed
Completed
Late July
10. Cleveland Area: Cleveland Ave. from Rice Street to 10th Street Completed
Completed Late June
11. Sertoma Area: Sertoma Ave from 26th to 41st Street In Progress Completed 2024
12. North Sanford Area: East of Grange Ave Between 13th Street and 18th Street Completed
In Progress 2024
13. Augustana Area: East of Grange Ave Between 26th Street and 33rd Street In Progress
In Progress 2024
14. Foss Area: Foss Ave from 6th Street to 15th Street Completed
Completed 2024
15. 41st & Bahnson Area: East and West of Bahnson Ave Between 37th Street and 41st Street In Progress
Completed 2024
16. Southeastern & Fireside Area: Southeast of 49th Street and Southeastern Ave Completed
Mid-August 2024

FAQs

If your sprinkler system needs to be repaired because of the curb and gutter installation, we apologize for the inconvenience. Sprinkler damage is sometimes unavoidable during curb and gutter repairs due to the proximity of the heads to the work area. Please contact us to get more information on the process to get it repaired.

Where concrete repairs are made, disturbance to lawns is an inevitable part of the process. The contractor will reseed areas impacted by the concrete construction. If concrete repairs in your neighborhood are finished between June and August, seed will not typically be planted until the fall. We wait to reseed during these months because of the challenge for the grass to grow during this time.

Although the contractor will be responsible for watering for several weeks, we recommend that you supplement the contractor’s watering to accelerate grass growth. Turf grasses generally require 1 inch of water per week. Even with proper maintenance, it could take up to two years to reestablish the lawn to the preconstruction condition. You may take additional measures to expedite the restoration process such as overseeding, fertilizing, or weed control.

If weeds grow before the grass, please mow the restored areas and the grass will eventually catch up and fill the restored area. Typical lawn maintenance will control many varieties of nuisance weeds. The contractor will employ weed control measures, but some cannot be performed for several weeks after grass germination to protect the new grass.

The maintenance and repair of your driveway approach and the associated gutter are your responsibility. If your approach is in need of repair, now may be a good time to perform this work. Driveway approaches and associated gutter will not be replaced as a part of this project. In the picture below, the area shaded in blue (driveway approach and the gutter in front of approach) are the property owner’s responsibility.

If you choose to have your driveway approach replaced before the mill and overlay, you will not have to pay for the asphalt patch (18-inch area shaded in gray) that is typically needed when replacing the approach.

Please let us know if you plan on replacing your driveway approach before the asphalt overlay. The contractor performing the work will need to be bonded and insured and receive a permit from City Engineering before starting the repair.

Driveway approach

The Street Division will drop off an informational door tag to let you know when crews plan to mill, tack, and overlay your street. If you have any questions on the schedule for paving your street, contact the Street Division at 605-367-8255.

Occasionally, crews are working in an area where a graduation party or neighborhood rummage sale is scheduled. Due to the frequency of these events and limited time for construction, we unfortunately can’t avoid them all. If you have an event planned, let one of our team members know the details. We will try to avoid working in the area at that time. If work at that time is unavoidable, we will work with the contractor to be as accommodating as possible.

Overlay projects typically progress through the following steps:

  1. Spot Utility Repair
  2. Curb and Gutter Repairs, ADA Curb Ramp Installation
  3. Milling of Existing Asphalt
  4. Asphalt Overlay

Due to the number of neighborhoods where work occurs and number of contractors involved, there may be time between each phase because of the complexity of the project. We appreciate your patience and cooperation throughout the whole process.

Routine maintenance is the key to managing our street assets in a cost-effective manner. Well-timed maintenance (i.e., crack sealing, surface treatment, and mill and overlay) allow streets to stay in good condition and extend the life of the street. Here are some of the reasons we mill and overlay streets:

  • It is a cost-effective way to extend the life of a street. The new asphalt not only seals the street, but also provides some structural value.
  • Milling removes deterioration and helps to restore the street to its original shape.
  • Other needed improvements (i.e., sanitary sewer and concrete repairs) can efficiently be made in conjunction with this program. This allows for multiple benefits to the City’s infrastructure through the implementation of this program.
  • Although construction can be inconvenient at times, this program is far less invasive than a street reconstruction project.
  • The end product is aesthetically appealing, improves the ride, and extends the life of the street. 

Milling consists of grinding the top surface of the asphalt down approximately 2 inches to make room for a new layer of asphalt. The byproduct of this operation is a material known as ‟millings.” Millings can be reused in place of gravel in street construction or can be recycled at the asphalt plant to make new asphalt. The asphalt overlay takes place in the days following the milling operation.

You can drive on the street after it has been milled. The asphalt overlay will happen shortly after the street has been milled.

After we overlay a street, we have to close the street afterwards for a short period of time. Depending on air temperature, the street may remain closed for four to eight hours while the asphalt cools down. Barricades will be removed from the street when crews have determined the street is ready to be opened. Please continue to be patient and do not drive around barricades to access a street under construction.

After paving, asphalt can still be above 200°F. At this temperature, the new asphalt can be damaged by vehicles and people. Even when the street is back open to traffic, the new asphalt still may be susceptible to damage. In the first few days after paving, please avoid turning your tires while stopped to prevent the surface from tearing or scaring.

<iframe width="560" height="315" src="https://www.youtube.com/embed/Vj1Rp9erosw" frameborder="0" allow="accelerometer; autoplay; encrypted-media; gyroscope; picture-in-picture" allowfullscreen></iframe>

Contact Information

Project Managers 

Areas: Sertoma, Cleveland, Foss, 41st & Bahnson, and Southeastern & Fireside
Doug Hoy
dough@sayreassociates.com
(605) 940-1055

Areas: North Sanford and Augustana
Rollin Tiggelaar
Rtiggelaar@siouxfalls.org
(605) 367-8619

Areas: Cliff Avenue
Jason Kono
Marshall Engineering
jay.marshalleng@midconetwork.com
(605) 360-5839

Utility Work
Scott Knutson
Sknutson@siouxfalls.org
(605) 367-8647

Asphalt Paving Schedule
Shandy Dvorak
SDovorak@siouxfalls.org
(605) 367-8262

Asphalt Paving Areas: Batcheller Lane, Rough Rider, Fireside, Marson, Lewis Park, Westport, Pettigrew, and Cathedral

Mike Schmidt
Mschmidt3@siouxfalls.org
605-367-1894

Contractors

Concrete
Areas: North Sanford and Augustana
Carl V. Carlson Company
605-528-3530

Areas: Sertoma, Cleveland, and Foss
D & K Construction
605-400-1189

Areas: 41st & Bahnson and Southeastern & Fireside
Katzer Concrete
605-271-6093

Utilities Contractor
605 Companies
605-251-3185

Project Summary

The project will consist of curb and gutter repairs, spot utility repairs, accessible curb ramp improvements, an asphalt mill and overlay. Streets will generally remain open to traffic during concrete and utility work. However, during paving operations, streets will be closed and traffic detoured accordingly.