Southeastern Avenue Sewer Lining and Asphalt Mill & Overlay, Klondike Trail to 49th Street

Exhibit

Project Update 9/17/2020

  • The project is COMPLETE! with the asphalt lane repairs being completed on September 3rd.
  • Only minor clean-up items remain, which includes installing topsoil & seed at several locations along the project.
  • All streets are open to traffic.

Project Milestones

  • Sanitary manhole replacement
  • Sanitary sewer lining (CIPP)
  • Curb and gutter repairs
  • Installation of ADA compliant sidewalk ramps
  • Asphalt milling and overlay
  • Underdrain installation
  • Asphalt repairs for eastern northbound lane

Commuter Route Information

  • The Bike Trail along the west side of Southeastern Avenue is open for use. 
  • Southeastern Avenue will be closed to through traffic south of 26th Street.
  • Traffic will be detoured to Cliff Avenue and Sycamore Avenue.

 

Sign Up for Notifications

overview

Project Overview

Contract Amount: $3.69 million  

Completion Date: November 8, 2019

Project Summary

Work will be performed along Southeastern Avenue, south of the intersection of 26th Street & Southeastern Avenue; with the project work limits from Klondike Trail to 49th Street.  Major work items will include sanitary sewer manhole replacements, sanitary sewer lining (CIPP), curb and gutter repairs, ADA compliant sidewalk ramps, and asphalt milling & overlay.

Contact Information

City of Sioux Falls
John Osman, Project Manager
josman@siouxfalls.org
(605)-367-8640 (office)

Consultant 

HDR Engineering
Lance McQueen
Lance.McQueen@hdrinc.com 
(605) 977-7740 (Office)  
(605) 610-7955 (Cell)

Contractor Name

H&W Contracting, LLC