Tallgrass Avenue from 74th Street to 85th Street
Project Update 5/31/2023
- This project includes the necessary Storm drainage pipe on Tallgrass Avenue from 74th street to 85th street, grading and concrete paving at the intersection of 85th street and Tallgrass Avenue.
- City just acquired the necessary Right of way to construct this project.
- Project will be bidding in July.
Commuter Route Information:
- Tallgrass Avenue from 74th street to 85th street will be closed to traffic.
Project Milestones
- Road Closed
- Removals
- Sanitary sewer
- Watermain
- Storm Sewer
- Grading
- Subgrade Stabilization
- Gravelling
- Curb and Gutter
- Concrete Surfacing
- Restoration
- Open to Traffic
Project Overview
Completion Date:
December 2023
Contract Amount:
TBDProject Summary:
This project consists of work on Tallgrass Avenue and includes installation of storm sewer, minor sanitary sewer and watermain work curb and gutter, sidewalks, and concrete paving.
Contact Information
City of Sioux Falls
Vish Nellore
vnellore@siouxfalls.org
605-367-8643
Consultant Name:
DGR Engineering
Scott Lavoy
scott.lavoy@dgr.com
605-366-1679
Contractor Name:
TBD