Tallgrass Avenue from 74th Street to 89th Street

  • Contractor nameT&R Contracting, Inc.
  • Completion DateDecember 13, 2024
Tallgrass-74th-St-to-85th-St

Project Update 4/1/2024

  • Contractor is currently installing Fabric and Gravel Base course along 85th street.
  • Starting Monday April 1, 2024, contractor will be installing the underdrain along the Tallgrass Avenue between 74th street and 85th street. 

Commuter Route Information:  

  • Tallgrass Avenue from 74th street to 89th street will be closed to traffic.
  • Access will be maintained to local residents only.

Phase 1 Project Milestones

  1. Road Closed
  2. Removals
  3. Sanitary sewer
  4. Watermain
  5. Storm Sewer
  6. Grading
  7. Subgrade Stabilization
  8. Graveling
  9. Curb and Gutter
  10. Concrete Surfacing
  11. Restoration
  12. Open to Traffic

Phase 2 Project Milestones

  1. Road Closed
  2. Removals
  3. Grading
  4. Subgrade Stabilization
  5. Graveling
  6. Curb & Gutter
  7. Concrete Surfacing
  8. Lighting
  9. Restortion
  10. Open to Traffic